Project Description

Client: City of Allen
Location:  City of Allen, Collin County, Texas
Contract Value:  $372,000

John Burns Construction Company performed the emergency installation of a critical large diameter trunk main line that was leaking water in Allen, Texas.

The Challenges

  • Urgent Installation of 24-inch Bethany Water Line
  •  JBCC was faced with many challenges including working on the repair and installation at a major intersection that was once a rock quarry.
  •  JBCC successfully replaced 461 LF of 24” water main, 3 valves (including a size on size tap) and relocated storm lines in an environmentally sensitive area all while maintaining traffic on two of the City’s busiest thoroughfares.
  • This project was completed within the allotted time frame and avoided potential disruptions of water service to the City.