John Burns Construction Company successfully completed a site utility project for Balfour Beatty Construction in 2008 valued at $1,700,000.  This project was the extension of Underground Utilities to serve a new 25 story mixed use office building in the Dallas Central Business District.

•   Installed 1200 linear feet of 12” water mains.

•   Installed 900 linear feet of 12” and 15” sanitary sewer mains.

•   Installed 1400 linear feet of storm drain pipe.

•   Installed 2,000 linear feet of gas main piping.

•   Installed 1100 linear feet of 15 electrical conduit and manhole system.

•   All work was performed during normal business hours while streets remained open in the middle of the Dallas Central Business District.

Project details
  • , Categories:
  • Client:Balfour Beatty
  • Location:Dallas, Texas
  • Contract Value:$1,700,000
  • Completion Date:February, 2008